PCB Unloader loader and Destacker from production to packaging.
1. Purchase all kinds of materials according to order.
2. Frame installation of the entire machine.
3. Installed power motor
4. Install PLC control box.
5. Install sensor and belt.
6.Install the cover
7.Install the LOGO
8. Install the program and test the machine.
9 .Use PCB board to test machine.
10.Use a magazine test machine.
11. Aging operation week
12. Simple packing before shipment.
13. On the day of shipment, use the export wooden box vacuum packing,
14. Arrange forwarders to pick up the goods.
Four machines were shipped and shipped to the United States via freight forwarders.