PCB board handling system Destacker Build Procedure

2023-02-09 17:51:23

Destacker Build Procedure    SDM0029
Rev
A

 

 

1.    Obtain the proper shop packet and check order for build information. Pull all parts if any parts are missing,         fill out a shortage sheet and give a copy to the appropriate material coordinator.

 

2.    Pull the latest Electrical and Mechanical prints.

 

3.    The following procedure is for a 29″ Destacker. Attach leg and control box to main beam. Leg should be flush to         left side of main beam. Control box should be 3″ from right side of main beam. Attach width units to main beam,         4-3/8″ from either end square to main beam and Parallel to each other.

 

4.    The following procedure is for the 44″ and 58″ Destackers Attach leg and control box to main beam. Leg 7-5/8″ from     left end control box 7-5/8″ from right end. Attach width units to main beam 8.975″ from either end. Square to main         beam and parallel to each other.

 

5.    Attach rear rail to width supports parallel to main beam 3/8″ overhand from either end of main beam.

 

6.    Level conveyor from side to side and front to back, off rear rail

 

7.    Attach front rail to width supports. Match level to rear rail, especially front to back. Make parallel to rear rail. Make         ends even with rear rail.

8.    Install motors, pulleys, UHMW and belts on rails.

 

9.    Attach Destacker assy to rails

 

10.    Assemble valve pack assy and install

 

11.    Attach air input assy

 

12.    Attach front cover and wire into control box

 

13.    Run pneumatic lines, load program software and test.

 

14.    Complete check sheet, turn over to QC

 

 

End of Document

 