STEP & DESCRIPTION |
Builder |
||||||||||||
|
Check base casting build. |
|
||||||||||||
|
Thompson shaft oriented torqued and lubed with 10w oil. |
|
||||||||||||
|
Leveling pads mounted but not tightened. |
|
||||||||||||
|
Foam insulation in place. |
|
||||||||||||
|
Check y & x frame build. |
|
||||||||||||
|
Bearings & retainers mounted |
|
||||||||||||
|
Verify the x & y bearing preloads are set. |
|
||||||||||||
|
Limit rails and limit blocks mounted and activate limit switches. |
|
||||||||||||
|
Tie clamps mounted. |
|
||||||||||||
|
All brass pneumatics fittings installed. |
|
||||||||||||
|
Insure base, y frame, and x frame are mated together. |
|
||||||||||||
|
Check build & installation of x & y paddles. |
|
||||||||||||
|
Hardware tight dowels in place. |
|
||||||||||||
|
Bearings installed. |
|
||||||||||||
|
Check x & y table movement. |
|
||||||||||||
|
Ball screw units installed and lubed. |
|
||||||||||||
|
Motor, drive belt installed with proper belt tension adjusted. |
|
||||||||||||
|
Rotary disc installed. |
|
||||||||||||
|
Wheels mounted with proper hardware and internal tooth CSK. |
|
||||||||||||
|
Lock assy & drive motor installed & adjusted. |
|
||||||||||||
|
Wheel cams adjusted so dowel pins fit through disc bushings into the x-frame bushings. |
|
||||||||||||
|
|
|