Контроль качества
В этом разделе описывается сертификат производительности станка, являющийся результатом приемочного испытания качества (QAT), который выдается для всех продуктов Axial.
Каждый станок Axial перед отправкой заказчику подвергается приемочному тесту качества (QAT). В QAT есть 4 этапа:
Фаза I – Цикл предварительной сушки
The appropriate pattern program is loaded and the machine performs a short part run with all motions and mechanisms functioning to check setups and speed. All data is recorded on the machine's event log.
Phase II – Dry Cycle
Can only occur after successful completion of the Pre-Dry Cycle. The machine is run with all motions and mechanisms functioning but without boards or inserting components for a pre-specified period of time. All data is recorded on the machine's event log.
Phase III – Integrity Run (Final Run)
Can only occur after successful completion of the Dry Cycle. This is a simulated production run to check insertion performance and speed. Results are recorded on the machine's event log.
Sequencer 6 2596C | VCD/Seq. 8 6241F |
DH VCD 8 6292C/ 6298C |
DH JW 8 6293C/ 6299C |
Radial 8 6380A/6388A |
|
Phase I |
|
|
|
|
|
Parts Run |
2,400 |
2,100 |
2,400 |
2,400 |
500 |
Insertion PPM * |
0 |
0 |
0 |
0 |
0 |
Intrinsic Availability ** |
100% |
100% |
100% |
100% |
100% |
Phase II |
|
|
|
|
|
Length of Run |
2 hrs. Viagra Original |
24 hrs. |
12 hrs. |
12 hrs. |
12 hrs. |
Intrinsic Availability |
95% |
95% |
95% |
95% |
95% |
Phase III |
|
|
|
|
|
Minimum Parts Run |
11,939 |
22,306 |
26,765 |
43,299 |
30,680 |
Allowable Insert Errors |
0 |
1 |
0 |
0 |
4 |
Intrinsic Availability |
95% |
95% |
95% |
95% |
95% |
Acceptable PPM Levels |
34 – 250 |
10 – 200 |
40 – 150 |
7 – 75 |
300 |
Confidence Level |
95% |
95% |
95% |
95% |
95% |
- (# of good insertions / total # of insertions)
** (# of hours the machine is ready to run / total # of hours machine planned to run)
Phase IV – Customer Acceptance (Optional)
Can only occur after successful completion of the Integrity Run. The customer visits the factory to watch verify the machine's ability to meet performance requirements. The customer's production run is simulated and all options are verified and explained. UIC can supply the PC boards, pattern programs and components or the customer may supply these items. (Must be supplied two weeks prior to the customer acceptance date.)
Phase V – Preproduction Acceptance (At customer site)
UIC Field Service personnel installs the machine and assures it is setup and running with the same degree of operational efficiency as at the factory.
Каждая машина отправляется заказчику вместе с Сертификатом производительности машины, являющимся результатом приемочного испытания качества (QAT). Этот сертификат подтверждает результаты QAT, характеризует наш производственный процесс и подтверждает нашу приверженность качеству и удовлетворенности клиентов. (См. прилагаемый образец копии.)
Пожалуйста, будьте осторожны при обсуждении этой информации с клиентами!! Эти результаты QAT, особенно уровни PPM, являются индикатором качества работы машин, которые мы отправляем, но фактическая производительность в производственных средах клиентов будет варьироваться в зависимости от их настроек и обслуживания, как указано в руководствах UIC. Очевидно, что клиенты, которые следят за нашими процедурами по эксплуатации, настройке и техническому обслуживанию машин, должны рассчитывать на средние уровни PPM, определенные в QAT для каждой машины.